Almost a month after work on the Sohna road project was suspended over safety violations found by the National Highways Authority of India (NHAI), construction has resumed on a small section this week.
“Right now, we have allowed work on a length of about 600 metres where safety requirements have been met. For other stretches, we will allow work once the safety standards are complied with,” said an official from NHAI.
The Sohna road project, to be completed by July 2021, involves the six-laning and strengthening of a 21-km stretch between Rajiv Chowk and Sohna, through the creation of flyovers and underpasses at multiple points.