The hydel projects run by the Punjab State Power Corporation Limited (PSPCL) surpassed electricity production target set by the Central Electricity Authority (CEA) for the first quarter of the 2020-21 fiscal year.
PSPCL chairman-cum-managing director (CMD) A Venu Prasad said the hydel projects generated 1,419 million units against the target of 1,055 million units in the April 1-June 30 quarter.
“The Mukerian project generated 380.18 million units against the target of 118 million units (322% of the target), the highest in the last eight years. The Anandpur Sahib project generated 198.34 million units against the target of 168 million units (118% of the target),” he said.