The Brihanmumbai Municipal Corporation (BMC) has completed 330 metres of tunnelling work of the underwater twin tunnels, connecting the 9.98-km Princess Street Flyover with Worli, which are a crucial part of the coastal road project.
The first 100 metres of the tunnelling was completed by BMC in the first week of March.
The overall tunnelling work is expected to take 18 months and BMC has set a deadline of June 2022 for the completion of the work.
The two tube twin tunnels will start run below Girgaum Chowpatty and come out at Priyadarshani park.
According to BMC officials, the twin tunnels are being built using the cut-the-cover construction method, wherein the actual tunnel would be only 1.9km, but after including the entire entry and exit portions, its length would run up to 3.4km.