MUMBAI: The eight-lane widening project for Nahur road over-bridge (ROB) completed a crucial phase early on Sunday as two more girders were launched. Eight girders have been installed till now, with four on either side of the existing old ROB.
Girder launching
216 ton: Weight of each girder
72 metre: Length of each girder (same as ROB length)
– The seventh and eighth girders were launched for Nahur ROB during a three-hour rail block from 1.20-4.20am on Sunday.