Noida Power Company Ltd (NPCL) has claimed that the work of setting up multi-point power connections in Greater Noida is in full swing in pursuance of an order issued by the UP Electricity Regulatory Commission (UPERC).
“So far, the multi-point implementation work in 18 societies has been nearly completed. NPCL has sent notices to 134 societies regarding multipoint connections; 88 societies have requested that single-point connections be maintained for the time being,” said a company spokesperson.
NPCL, according to him, recently conducted a survey in many societies, in which it was found that 20 societies did not have the necessary infrastructure for multipoint connections. “NPCL is in talks with these societies, and it is expected that after necessary infrastructure is in place the work of setting up multi-point connections in about 10 societies will begin soon,” he added.