Infrastructure firm Megha Engineering and Infrastructures (MEIL) has secured a place in ‘Limca Book of National Records’ by completing a complex power substation project in incompatible weather conditions in nearly half the stipulated timeframe.
The 400/220KV power substation for Power Grid CorporationNSE 2.86 % was built in a record time of seven months, which is five months ahead of the scheduled deadline while fulfilling all the quality parameters, said MEIL in a statement.
The project at NP Kunta in Ananthapur district of Andhra Pradesh normally takes 15-18 months for execution but “MEIL could complete it within a span of 7 months as per Power Grid Corporation requirements,” said MEIL director B Srinivas Reddy. “To achieve this record breaking performance, we mobilised additional resources, machinery. At the same time our engineers and field staff worked for three shifts (24 hours).”