Construction of five piers on the Shyambazar-end of the Tallah bridge and two on the Dunlop-end will be over by March 2021, the state government has decided after a recent review of the pace of work of one Calcutta’s biggest infrastructure projects in the north.
PWD engineers have been accordingly briefed and a blueprint on the work to be done over the next three months has been readied.
The foundation for construction of two of the six piers that will come up between railway tracks will also be over by March-end, senior officials in the know said.