ROURKELA: The delay in land acquisition and removal of encroachments has stalled the much-awaited road over bridge (ROB) project at Rajgangpur level-crossing in Sundargarh district. Jointly taken up by the Odisha government and the South Eastern Railway (SER), the under-construction project is running at least 26 months behind schedule. While the Works department is yet to start construction on its 570-metre stretch which includes approach roads at both ends, the SER has made significant progress in its work on the central portion of the ROB over the tracks on the highly-busy Howrah-Mumbai main line.