The daily ridership numbers of the Gurgaon Rapid Metro is not even 10 per cent of the figure projected while conceptualising it, an official report has shown leading a senior IAS officer in Haryana to demand a probe in the entire manner in which the project was planned and implemented.
Documents reveal that from October 23, 2019 till March 21, 2020, the Rapid Metro’s 11.7-km line operated for 151 days with a total ridership figure of 76,41,367. After that the Metro stopped operating due to Covid-19 lockdown restrictions. The Metro restarted operations from September 7, 2020 and till March 31, 2021 – for 206 days – it garnered a total ridership of 16,08,005. The total ridership figures for this 357-days period was 92,49,372.