The first phase of the Mumbai coastal road — from Marine Drive to Worli — is likely to be ready by November 2023, a senior official of the Brihanmumbai Municipal Corporation (BMC) said on Friday.
The total estimated cost of the project, being constructed by the BMC, is Rs 12,721 crore. Phase I, the 10.58 km stretch from Marine Drive to Worli in south Mumbai, would be operational by November, BMC chief engineer M M Swami told reporters. As much as 71 percent work is complete, he said. Tunnel boring work is 91 percent complete, reclamation 93 percent, retaining wall 79 percent, interchanges 36 percent and bridges are 32 percent complete, Swami added.