Anticipating a harsher winter this year, discoms have estimated that the national Capital’s power demand will go up to 5400 MW, surpassing the peak winter demand in the previous two years, officials said.
Last year, Delhi’s peak power demand in winter had peaked to 5021 MW and in 2019 it was 5343 MW, discom officials said.
A BSES spokesperson said the peak winter power demand in BRPL and BYPL areas had reached 2091 MW and 1107 MW respectively during last winter. This year, it is expected to reach 2315 MW and 1140 MW for BRPL and BYPL respectively.
Accurate demand (load) forecasting is critical for reliable power supply. It is done on various parameters like day-ahead, intra-day basis and medium term (from a fortnight to one year).