As many as 725 road projects of the total 1,801 ongoing projects are running behind the schedule across the country as of February 2023 due to protracted monsoon in many states and above-average rainfall in some states, Union minister Nitin Gadkari said on Wednesday.
The Road Transport and Highways Minister in a written reply to the Rajya Sabha said additional cost is not incurred in all delayed projects as in Build-Operate-Transfer (BOT) projects, as escalation cost is absorbed by the Concessionaire.
For other projects, if the delay is attributable to the Project Authority, price escalation is paid as per contract conditions, which may or may not result in additional cost,