MUMBAI: The Brihanmumbai Municipal Corporation (BMC) on Wednesday confirmed the progress of its highly ambitious Mumbai Coastal Road Project (South) and said 58 per cent of the total work has been completed so far.
A total of 107 hectares out of the total 111 hectares of reclamation have been completed constituting 97 per cent of the project. Similarly, 70 per cent of work on the sea wall has also been completed. Out of the 175 monopiles to be constructed under the bridges, 40 per cent constituting 70 units.