As many as 423 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.95 lakh crore, as per a report.
According to Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,568 projects, 423 reported cost overruns and as many as 721 projects were delayed.
“Total original cost of implementation of the 1,568 projects was Rs 21,59,802.67 crore and their anticipated completion cost is Rs 26,54,818.05 crore, which reflects overall cost overruns of Rs 4,95,015.38 crore (22.92 per cent of original cost),” the ministry’s latest report for May 2022 said. According to the report, the expenditure incurred on these projects till May 2022 is Rs 13,42,535.22 crore, which is 50.57 per cent of the anticipated cost of the projects.