Baiyappanahalli-Whitefield metro line trial from October 25
Trial run on the Baiyyappanahalli-Whitefield section of Namma Metro Phase 2 extension is likely to begin from October 25 as the BMRCL races to meet the deadline to launch the stretch.
Last week, the Bangalore Metro Rail Corporation Limited (BMRCL) issued a public notice on test-charging 33 kV cables running along the metro viaduct between Whitefield and KR Puram. The cable network will be tested from October 15 onwards.
“Trial runs will be conducted for at least 45 days, following which we will request for inspection by the Commissioner of Railway Safety. If everything goes as planned, the line will be thrown open for the public at the beginning of 2023,” an official said.