UPEIDA CEO reviews progress of B’khand e-way; 69% work done

Lucknow: Around 69% physical work of Bundelkhand expressway has been completed and 687 structures out of 818 along the expressway have already been constructed.

Presiding over virtual meeting of the Bundelkhand Expressway Awanish Awasthi, CEO,UP Expressways Industrial Development Authority (UPEIDA), on Thursday instructed officials to expedite construction work of Toll Plaza and toilet boxes along the expressway.

During the meeting, officials also informed that out of 296.07 km of the expressway around 213.03 km of the road has been constructed.

During the meeting, officials apprised the CEO, UPEIDA, that construction work of all 14 long bridges on the expressway and four railway-over-bridges was progressing as per the schedule.