Silkyara tunnel rescue: Vertical drilling of 20 metres done on first day
Rescuers began drilling into the hill above the Silkyara-Barkot tunnel Sunday, boring nearly 20 metres on the first day of adopting the new approach to reach 41 workers trapped inside for 14 days.
The vertical approach was one of the at least five options on which preparatory work had begun some days back, as anxiety mounted over the fate of the men trapped in the under-construction tunnel on Uttarakhand’s Char Dham route.
Rescue workers have to drill down 86 metres to reach the tunnel. By evening, the heavy drilling equipment had bored down to about 19.5 metres.