SC: Expert panel must assess need for overhead power lines in GIB areas
An expert committee should assess the need and feasibility of installing overhead power transmission lines before constructing any new overhead power transmission lines passing through the habitat of Great Indian Bustard (GIB) in Rajasthan and Gujarat, the Supreme Court has directed power infrastructure developers.
The apex court has also set the deadline of July 20 for completing installation of bird diverters on all existing overhead power lines in the GIB habitat.
Hearing public interest litigation (PIL) filed by retired IAS officer MK Ranjitsinh and others, the SC directed that injunctions, imposed by the apex court in its order dated April 19, 2021, on new overhead power lines in priority and potential GIB habitats “be scrupulously enforced”.