Renewable energy projects get 30 days extension for commissioning beyond lockdown period
New Delhi: The Ministry of New and Renewable Energy (MNRE) has granted an extension of 30 days for commissioning of renewable energy projects beyond the lockdown period. The renewable energy implementing agencies may grant extension of time for commissioning of such projects, impacted due to coronavirus lockdown, equivalent to the period of lockdown and additional 30 days for normalisation beyond the curb period, the ministry said in a statement on Tuesday.
This will be a blanket extension and there will be no requirement of case to case examination, as also there will be no need to ask for any evidence for extension due to