RE Integration: Gas power a way out of RE woes
That renewable energy (RE) faces challenges like uncertainty and intermittency of supply, making electricity load management units across the country reluctant to draw it, is well known. What is less known is the role gas-based power—of which India has under-utilised capacity—can play to smoothly integrate RE in the grid system, given that it can be ramped up and down much faster than other conventional sources.
To put this advantage gas generation enjoys into perspective, while the ramp-up rate for coal-based power plants is around 2% per minute, it is as high as around 6% for gas-based power plants. This was evident during the solar eclipse on June 21 last year when hydro and gas generation had to be ramped up by 30% and 13%, respectively, to make up for a 28% fall in renewable power. Later, when RE was ramped up by 37%, hydro and gas power supply could be immediately brought down by 18% and 17%, respectively, with coal-based power not being of much use in load adjustment.