Pune ring road: Survey of 9 villages done, 37 remain in eastern sector

PUNE: Since beginning the joint measurement survey (JMS) for the eastern part of the Pune ring road on August 17, officials of the Maharashtra State Road Development Corporation (MSRDC) have completed the procedure in only nine out of the 46 affected villages. Whereas, the land survey of only three out of the 37 affected villages remains to be completed for the western part of the ring road after which officials aim to complete the land acquisition process for this part by December this year. On September 6, the state government approved a budget of Rs26,831.21 crore for the Pune ring road project which includes construction and land acquisition costs.