KOCHI: Reconstruction work of Palarivattom flyover will begin on Monday as Delhi Metro Rail Corporation (DMRC) and Uralungal Labour Contract Cooperative Society (ULCCS) Ltd held a meeting to finalise the procedures for beginning the demolition work as part of the reconstruction. ULCCS chairman Rameshan Paleri said they had a discussion with the DMRC on finalising the date for commencement of the work and it will begin on Monday.

The demolition will be held in different phases and steps will be taken to ensure free flow of traffic through the stretch. Majority of the work will be carried out during night time and a proper action plan will be put in place when spans and pier caps are demolished. The reconstruction will be carried out as per the project report prepared by Metroman E Sreedharan. It will take eight months for the reconstruction of the flyover.