Mundra LNG terminal to be commissioned by December
NEW DELHI: More than a year since its inauguration, Gujarat government-backed LNG project at Mundra, built at an estimated cost of Rs 5,500 crore, may finally get commissioned by December, according to sources.
A commercial dispute between the partners Gujarat State Petroleum Corp (GSPC) and Adani Group had stalled commissioning of the 5 million tonnes a year liquefied natural gas (LNG) import facility, they said.
The terminal was mechanically completed in mid-2018 and was inaugurated by Prime Minister Narendra Modi.