THE MUMBAI Metro Line 2A (Dahisar to DN Nagar) and Line 7 (Dahisar East to Andheri East) have cleared the RDSO (Research Designs and Standards Organisation) testing and will now undergo testing for signalling, according to an MMRDA official.

“The RDSO test is an important milestone that has been achieved. In the next few days, the certification will be issued. Now the target to finish the remaining safety clearance is we are processing, so that commissioning of the remaining stretch by the end of this year is achievable,” the official added, requesting anonymity.

RDSO clearance is an important first step for any Metro rail line for commercial operation to start.