Mumbai: Litigations delaying Metro car shed project and causing loss of public money, HC told
The Mumbai Metro Rail Corporation Limited (MMRCL) on Thursday told the Bombay High Court that the construction of the car shed at Aarey Colony was getting delayed and causing loss of public money due to litigations, defending its plan to cut more trees at the site than earlier proposed.
MMRCL, a nodal agency, told the HC that due to the court cases, it could not cut down trees in 2019 and this has now led to an increase in the number of trees that are required to be cut for the project at suburban Goregaon. In 2019, the MMRCL had sought permission from the tree authority of the Brihanmumbai Municipal Corporation (BMC) to chop 84 trees.