LESA fast-tracks ₹15 cr power project for VVIP Mantri Awas area
Following repeated complaints of power outages from residents of the high-profile Mantri Awas area, LESA expedited a ₹15-crore underground cabling project to ensure uninterrupted power supply to the Mantri Awas substation in Vibhuti Khand, Gomti Nagar.
Officials on Tuesday completed the laying of a 9-km-long underground 33 KV cable from the Satrikh and the transmission substation.