Jewar Airport begins to spread wings: Work force, machines increased; Yogi takes stock

The first stage of construction of Noida International Airport at Jewar is expected to be completed by January 2024, Dr Arun Vir Singh, Chief Executive Officer, Noida International Airport Ltd, said Tuesday. To meet the target, the workforce is being increased from 700 at present to 4,000, and machinery from 39 at present to 400 this month.

“UP Chief Minister Yogi Adityanath visited the airport site Sunday and took stock of the current status of construction in stage 1. For stage 1, around 1,334 hectares of land was fully acquired in 2020. The terminal building and one of the runways has been constructed. As of now, construction of boundary wall is complete at 93%.