Himachal CM asks officials to ensure timely completion of power projects

Himachal Pradesh Chief Minister Thakur Sukhvinder Singh Sukhu has instructed the state’s energy department officials to ensure the timely completion of the power projects in the state.

He emphasized the need to expedite them at an official meeting presided over by him at Hamirpur on Saturday.

The Chief Minister said that the delays in the completion of the power projects are causing financial losses for the state’s exchequer.

During the meeting, the Chief Minister said that the state aims to commission 628 MW of hydroelectric projects by March 2027. This includes the completion of the 450 MW Shongtong Karchham project by July 2025, the 48 MW Chanju-3 Hydro Electric project by March 2027 and the 130 MW Kashang-2 and 3 projects by June 2026.