Highways dept disputes report on flyover
The State Highways Department has disputed the facts in the report headlined ‘Flyover ready, waits for minister’ in these columns on June 21. P Selvanambi, divisional engineer, Chennai Metropolitan Development Plan, writes that the news is baseless.
“It is furnished that the following works are pending and in progress as far as SR Nagar Arm is concerned: 1. The service road portion adjacent torailway portion is in progress. 2. Shifting of BSNL cable and widening of service road under the bridge portion is in progress.3. Fixing of cat’s eyes and road safety works including road marking is under progress. 4. The drain work near culvert portion is under progress. 5.