Highway construction slows to 19 km/day during Apr-Aug: MoRTH

The pace of national highway construction in the country has slowed to 19 km per day during the first five months of the current financial year, according to official data.

While the pace of national highway (NH) construction in the country had touched a record 37 km per day in 2020-21, it had slowed to 28.64 km a day in 2021-22, due to pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country.

“The Ministry has constructed 2,912 km of National Highways up to August 2022, as compared to 3,355 km up to August last year. The Award figure is 2,706 km during this period as compared to 3,261 km in the previous year,” the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for August 2022.

Read more

You may also like

Comments are closed.