Faulty tender conditions for Metro project resulted in undue benefit of ₹4.36 crore to contractors, finds CAG

The Comptroller and Auditor General (CAG) of India has pulled up the Maharashtra government for its poor performance in the implementation of Rashtriya Uchchatar Shiksha Abhiyan (RUSA). The report for the year ending March 2021, which was tabled in the state legislature on Friday, also pointed to faulty tender conditions for the Metro project in Mumbai leading to an undue benefit of ₹4.36 crore to contractors.

The CAG report in its findings found that the delay in constituting State Higher Education Council (SHEC), a policy body for higher education, the delay in creation of universities by converting colleges into a cluster, and the low spending on higher education made the implementation of RUSA in Maharashtra ineffective and weak.

“The implementation of RUSA in Maharashtra was fraught with delays and ineffective monitoring… The government decided to participate in its implementation in October 2013.

Read more

You may also like

Comments are closed.