DMF funds projects execution slow in mining dists
There has been tardy progress in the implementation of projects under the District Mineral Foundation (DMF) funds in the State.According to the Government of Odisha’s Rural Development Department Annual Activity Report (2020-21) tabled in the State Assembly on Saturday, four important DMF active districts, such as Keonjhar, Sundargarh, Jajpur and Koraput, have made some progress even though they are lagging behind on the project implementation front. Assessments were done on three important infrastructure, road, bridge and building.
It is revealed that out of 222 approved road projects, 94 projects are completed and work is under progress in 91 projects. While out of Rs 56,196 .96 lakh sanctioned, utilisation certificates (UCs) have been given in respect of only Rs 18,817.57 lakh though the spending is to the tune of Rs 23,763 lakh.