Delay in PR-7 road construction reason behind traffic snarls

With the construction of PR-7 road connecting Zirakpur and Panchkula hanging fire, a solution to the traffic woes of the residents seems difficult. The 4 kilometer stretch of the road could not be completed due to a delay in the acquisition of the forest land in Peermuchalla.

The 11 kms stretch will connect Panchkula in sectors 24 and 26 with Zirakpur and with the Airport Road. The road was constructed to decongest Zirakpur towns and to divert the traffic coming from Delhi towards Shimla. However, the work on the road from Panchkula has been completed.

The Greater Mohali Area Development Authority (GMADA) and Public Works Department (PWD) were to construct the road stretch.