Days after closing it, BMC in a fix over who will demolish Gokhale Bridge
Four days after it shut down Gokhale Bridge for pedestrian and vehicular movement, the BMC is no way close to finding out how it should go ahead with demolishing the structure even as common Mumbaikars face the brunt of an extremely chaotic traffic situation.
At present, the BMC and the Western Railway (WR) are yet to take a decision on who will demolish the bridge.
P Velrasu, additional municipal commissioner (Projects), told The Indian Express on Thursday that BMC and Railways officials will meet on Friday. He added that the delay in starting demolition work was due to the fact the Railways has always demolished bridges that run above rail tracks and the BMC has no prior experience in demolishing such bridges.