CAG red flags slow development of hydro power projects in Jammu and Kashmir

The Comptroller and Auditor General (CAG) said out of 374 identified project sites with power generation capacity of 1,725.53 MegaWatts, only 10 projects with 79.75 MW capacity had been commissioned with time overrun ranging between four months and seven years.

The hydro power potential of Jammu and Kashmir has been estimated at 20,000 MW which includes 1,500 MW in respect of small hydro projects. As of October 2021, only 2,813.46 MW (16 per cent) of this potential had been harnessed, which included 79.75 MW of small hydro projects.

“The main objective of hydro policy for small hydro project/mini hydro projects for expeditious development of available hydro power of Jammu and Kashmir was not achieved. Out of 374 identified project sites with power generation capacity of 1,725.53 MWs,