BHEL in focus: Secures Rs 15,000 crore order from MP, wins GST relief
By
Binu Mathew
Bharat Heavy Electricals (BHEL) received a significant work order on Tuesday. In an exchange filing, the company said that it has received an order worth Rs 13,000-15,000 crore from MP Power Generating Company.
BHEL stated that it has received an order for the Engineering, Procurement, and Construction of a 660 MW supercritical thermal power plant at Amarkantak Unit in Madhya Pradesh, as well as a 660 MW thermal power plant at the Satpura Unit of M.P. Power Generating.