As Baghjan fire rages on, OIL sets July 30 deadline
The repair of an Oil India Limited (OIL)-operated well in Baghjan in Assam’s Tinsukia district which has been on fire since June 9, is down to a matter of replacing nuts and bolt-like studs and injecting a kill-fluid into the well, which is expected to be completed by July 30, a company spokesperson said Monday.
New studs, fabricated at OIL’s Duliajan workshop, have been transferred to the site to replace those that were damaged and deformed in the blaze, a statement released by the company on Monday said.
The blowout — – an uncontrolled release of gas and oil condensate — which occurred on May 27 has killed two firefighters, and caused a fire that has destroyed adjoining homes, injured three foreign experts examining the wellhead, and displaced at least 9000 people in the district, who have moved to relief camps.