A first for PSUs: NHPC acquires Lanco’s Teesta-6 hydro project under IBC

In a first instance of a state-run company acquiring a stressed asset under the insolvency and bankruptcy code, NHPC on Friday signed an agreement to take over and implement the 500-MW Teesta-6 hydro electric project in Sikkim. The project was being developed by Lanco Energy but progress had stalled since April, 2014 due to funds constraints with the company.

According to the resolution plan approved by the Hyderabad National Company Law Tribunal (NCLT) bench, NHPC would pay Rs 897.5 crore to the project’s financial creditors. Including the bid amount, the total estimated cost of the project — expected to be completed in five years — is seen to be Rs 5,748 crore.