443 infrastructure projects hit by cost overrun of Rs 4.92 trillion in Feb

As many as 443 infrastructure projects, each entailing an investment of Rs 150 crore or above, were hit by a cost overrun of more than Rs 4.92 trillion in February 2024, an official report stated.

According to the Ministry of Statistics and Programme Implementation (MoSPI), which monitors infrastructure projects worth Rs 150 crore and above, out of 1,902 projects, 443 reported cost overruns and 764 projects were delayed.

“Total original cost of implementation of the 1,902 projects was Rs 27,08,030.44 crore, and their anticipated completion cost is likely to be Rs 32,00,507.55 crore, which reflects overall cost overruns of Rs 4,92,477.11 crore (18.19 per cent of original cost),” the ministry’s latest report for February 2024 said.

Read more

You may also like

Comments are closed.