438 infrastructure projects show cost overrun of Rs 4.34 trillion

As many as 438 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.34 lakh crore, according to a report.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above. Of the 1,680 such projects, 438 reported cost overruns and 539 were delayed.

“Total original cost of implementation of the 1,680 projects was Rs 21,74,182.86 crore and their anticipated completion cost is likely to be Rs 26,08,330.02 crore, which reflects overall cost overruns of Rs 4,34,147.16 crore (19.97 per cent of original cost),” the ministry’s latest report for October 2021 said.

Read more

You may also like

Comments are closed.