386 infra projects show cost overruns of Rs 4.7 L cr

As many as 386 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.7 lakh crore, as per a report.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,505 projects, 386 reported cost overruns and as many as 661 projects were delayed.

“Total original cost of implementation of the 1505 projects was Rs 21,21,793.23 crore and their anticipated completion cost is likely to be Rs 25,92,537.79 crore, which reflects overall cost overruns of Rs 4,70,744.56 crore (22.19% of original cost),” the ministry’s latest report for July 2022 said.

Read more

You may also like

Comments are closed.

More in Newspapers