Due to impact of the COVID-19 pandemic, “fresh targets” have been set for Ph-IV project of the Delhi Metro, and the first section of a priority corridor is planned to be opened by July 2024, DMRC chief Vikas Kumar said.
In an interview to PTI, Kumar also said that besides commissioning of a small 2.5-3 km segment of the Janakpuri West-R K Ashram Marg corridor, the whole Majlis Park-Maujpur corridor is planned to be opened by March 2025.
The managing director of the Delhi Metro Rail Corporation (DMRC) said the construction of the Ph-IV has brought many firsts for the country,