{"id":531958,"date":"2022-10-26T11:01:51","date_gmt":"2022-10-26T05:31:51","guid":{"rendered":"https:\/\/infralive.com\/web\/?p=531958"},"modified":"2022-10-26T13:04:18","modified_gmt":"2022-10-26T07:34:18","slug":"384-infra-projects-show-cost-overruns-of-rs-4-52-lakh-crore","status":"publish","type":"post","link":"https:\/\/infralive.com\/web\/384-infra-projects-show-cost-overruns-of-rs-4-52-lakh-crore\/","title":{"rendered":"384 infra projects show cost overruns of Rs 4.52 lakh crore"},"content":{"rendered":"<p>As many as 384 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.52 lakh crore, as per a report.<\/p>\n<p>According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,529 projects, 384 reported cost overruns and as many as 662 projects were delayed.<\/p>\n<p>\u201cTotal original cost of implementation of the 1529 projects was Rs 21,25,851.67 crore and their anticipated completion cost is likely to be Rs 25,78,197.18 crore, which reflects overall cost overruns of Rs 4,52,345.51crore (21.28% of original cost),\u201d the ministry\u2019s latest report for September 2022 said.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>As many as 384 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.52 lakh crore, as per a report. According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,529 projects, 384 reported cost overruns and as many as 662 projects were delayed. \u201cTotal original cost of implementation of the 1529 projects was Rs 21,25,851.67 crore and their anticipated completion cost is likely to be Rs 25,78,197.18 crore, which reflects overall cost overruns of Rs [&hellip;]<\/p>\n","protected":false},"author":40,"featured_media":0,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[130,213,144],"tags":[],"class_list":["post-531958","post","type-post","status-publish","format-standard","hentry","category-newspapers","category-roads-the-pioneer","category-the-pioneer"],"acf":[],"_links":{"self":[{"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/posts\/531958","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/users\/40"}],"replies":[{"embeddable":true,"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/comments?post=531958"}],"version-history":[{"count":0,"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/posts\/531958\/revisions"}],"wp:attachment":[{"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/media?parent=531958"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/categories?post=531958"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/infralive.com\/web\/wp-json\/wp\/v2\/tags?post=531958"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}