Coal India announces provisional production and offtake performance

For month of September 2017
Coal India announced Provisional Production and Offtake Performance of the CIL and its subsidiary companies for the month of September 2017 and for April 2017- September 2017.

The Company achieved 101% of the targeted coal production at 38.77 million tonnes in September 2017. For the period April- September 2017, actual coal production was 95% of the targeted at 231.87 million tonnes.

Actual offtake was 103% of the targeted at 43.58 million tonnes in September 2017. For the period April- September 2017, actual offtake was 96% of the targeted at 269.02 million tonnes.