For month of September 2017
Coal India announced Provisional Production and Offtake Performance of the CIL and its subsidiary companies for the month of September 2017 and for April 2017- September 2017.
The Company achieved 101% of the targeted coal production at 38.77 million tonnes in September 2017. For the period April- September 2017, actual coal production was 95% of the targeted at 231.87 million tonnes.
Actual offtake was 103% of the targeted at 43.58 million tonnes in September 2017. For the period April- September 2017, actual offtake was 96% of the targeted at 269.02 million tonnes.